condo maintenance deficiency listcondo deficiency trackingcondo corporation maintenance13 November 2026

Condo maintenance deficiency list tracking

Track a condo maintenance deficiency list from walk-through to sign-off. Set up fields, statuses, photo evidence and the decisions people must make.

Condo maintenance deficiency list tracking

A condo maintenance deficiency list works when every item has a precise location, one owner, a clear status and proof that it was closed. Most lists fail on one of those four. The fix is not a longer spreadsheet. It is a tighter record and a regular review where a person decides what happens next.

This guide is for property managers working for condo corporations and for the maintenance contractors who do the work. It covers what to record, how to group items into jobs, who decides what, and how to close items so they stay closed.

What counts as a deficiency

In Canadian building work, a deficiency is an item that is incomplete, damaged or not performing as it should. In a condo, items usually come from three places:

  • Turnover or new-build deficiencies. Found when a newer building is handed from the developer to the corporation. These are often tied to warranty coverage.
  • Maintenance deficiencies. Found on routine inspections, by contractors on site, or through resident reports.
  • Project deficiencies. Left over at the end of a repair or renewal project, such as garage repairs or a corridor refurbishment.

Keep all three in one list and add a source field. Three separate lists means three places for an item to go missing.

Use the terms in your own governing documents. Ontario condo corporations talk about common elements. British Columbia strata corporations talk about common property. Quebec has syndicates of co-owners and common portions. The tracking method is the same.

One caution. New buildings may be covered by a provincial new home warranty program with its own forms and reporting deadlines. Those rules differ by province and they change. Check the current program guidance and take advice from the corporation's engineer or lawyer. This guide covers tracking, not warranty or legal advice.

What to record for each item

A vague entry creates a second site visit. Record enough that someone who has never seen the building can find the item and know when it is fixed.

  1. Item number. Unique, and never reused or renumbered.
  2. Location. Building, level, area and a fixed reference. For example: P2, stall 114, ceiling above the rear bumper line.
  3. Description. What you can see, not what you guess. Write "water stain on ceiling, damp to touch" and leave the cause to the trade.
  4. Before photos. One wide shot to show where it is, one close shot to show what it is.
  5. Source and date found. Inspection, contractor report, resident report or project close-out.
  6. Responsibility. Corporation, unit owner, developer or a contractor under warranty. If it is not clear, write "to be confirmed" and name who will confirm it.
  7. Priority. Safety, active damage, loss of function, or cosmetic.
  8. Assigned to. One named business or person. Never "maintenance".
  9. Target date. A real date, not "ASAP".
  10. Status. From a short fixed set, covered below.
  11. Close-out evidence. After photos, completion date and who checked it.

Keep the statuses short

Six statuses are enough for most buildings:

  • Open
  • Assigned
  • Scheduled
  • Done, awaiting check
  • Closed
  • On hold or disputed

The rule that matters most: the contractor can mark an item done, but only the manager or a named inspector can mark it closed. That one separation stops most repeat items.

Turn the list into jobs

Fifty items should not become fifty call-outs. Group them before you assign them.

Group by trade and location

Put all the garage drainage items together. Put all the door hardware items on one floor together. A contractor can then price and schedule one visit with a clear scope, and you can check one area in one walk.

Plan for access

Common-area items are simple to schedule. Items inside units or reached through units are not. Notice of entry must follow the corporation's governing documents and the rules in your province. Record access needs on the item so the contractor is not sent to a locked door.

Plan for the season

A lot of exterior work depends on weather. Sealants, masonry, paving and some roofing repairs may have to wait for warmer, drier conditions. Log the item now, set a realistic spring target date, and decide whether temporary protection is needed over the winter. An item parked for the season still needs an owner and a date.

Who decides what

A deficiency list is a decision tool. Software and spreadsheets hold the record. People make the calls.

  • The board approves spending beyond the manager's authority, as set out in the management agreement, and decides how larger repairs are funded, with professional advice.
  • The property manager sets priority, assigns the work, chases dates and closes items.
  • An engineer or consultant judges whether a repair is adequate where structure, building envelope or life safety is involved.
  • The contractor chooses the method, plans labour and materials, and reports hidden conditions as soon as they are found.
  • The unit owner provides access and deals with items that are their responsibility under the governing documents.

If an item is stuck, it is nearly always waiting on one of these decisions. Write down which one.

An illustrative example

This scenario is fictional and is here to show the method.

A manager walks the parking garage of a mid-rise Ontario condo in October and logs fourteen items. Six relate to drainage, five to lighting and three to concrete surface damage.

The manager groups them into three packages by trade. The lighting package goes to the electrical contractor with locations and photos, and a visit is scheduled. The drainage package needs a quote, so it sits at Assigned until the price is in and the board approves it. The concrete items are flagged for the engineer to look at before anyone prices a repair, and the manager adds a note about monitoring over the winter.

A month later the list shows five items closed with after photos, six waiting on a board decision and three waiting on the engineer. Nobody has to ask what is happening. The list says so.

Run a regular review

A list that is not reviewed turns into an archive.

  • Weekly, with contractors. Go through Assigned and Scheduled items. Confirm dates. Move anything that has slipped.
  • Monthly, for the board. Report the count by status, the items past their target date and the decisions you need from the board.
  • After every completed visit. Check the work in person or by photo, then close or reopen. Do not leave items at Done for weeks.

Keep closed items in the record. The history shows repeat defects and gives useful background when the corporation's reserve fund study or depreciation report is next updated.

Where Plan@Job fits

Plan@Job is AI-powered project and operations management for construction and property businesses. Property maintenance is one of its use cases.

Its project plan lets a job be split into internal stages, each with scope, dates, status and costs. Stages can be delivered by subcontractors or by in-house operatives. For deficiency work, one way to use that is to treat a grouped package as a job and its trades or areas as stages.

The client sees the overall agreed scope and price and the evidence shared with them. Internal stage costs and subcontractor identity stay internal to the operator, which is Plan@Job's term for the contractor business managing clients, delivery and subcontractors.

Plan@Job also has AI staff working in the background. Sophie Bennett, the AI Enquiries Coordinator, checks existing job briefs for missing information and asks for clarification, handing over to a person after two attempts. Daniel Reed, the AI Operations Manager, follows up on quotes and proposed dates and prepares a morning brief. They do not award work, set prices or move money. Those decisions stay with people.

The UK is the live market for Plan@Job at present. The features above describe the product as it runs there, and this article does not confirm availability or features for Canada.

Next step

If you manage condo buildings in Canada, check availability and reserve your place on the Plan@Job page for Canadian property managers. In the meantime, take your current list and add the two fields most often missing: a single named owner and close-out evidence.

FAQ

How is a deficiency list different from a work order log?

A work order log records requests and visits. A deficiency list records conditions in the building and follows each one until it is verified as fixed. One deficiency can need several work orders, and one work order can clear several deficiencies. Link them by item number.

Who should close a deficiency item?

Not the person who did the repair. The contractor marks the item done and supplies after photos. The property manager or a named inspector checks it and closes it. Where structure, envelope or life safety is involved, the engineer or consultant should confirm the repair first.

Is a spreadsheet enough to track deficiencies?

For a small building with one person keeping it up to date, it can be. It gets harder when several contractors need to update items, when photos live in separate folders, or when the board wants a current report. Whatever tool you use, the fields, the short status set and the review rhythm matter more than the software.