Before a Manchester replacement roof is covered, the coordinator in Dublin should receive the agreed evidence of the layers that will disappear and confirmation that the required local checks have happened. Agree those hold points before work starts. Asking for a photo of yesterday's hidden work is too late.
My back office is in Tangier, and I still do UK site visits myself. A remote file helps you ask better questions. It does not give you eyes under a finished roof.
Who decides what must be checked locally?
Ask the competent roofing lead and the relevant building control body to establish the inspection requirements for the actual job. Replacing roof coverings can need building regulations approval. GOV.UK approval guidance, checked 22 November 2026.
For an ordinary house, establish the appropriate building control route before work starts. GOV.UK directs applicants to a building control body to check requirements and apply. GOV.UK application guidance, checked 22 November 2026.
Name the person controlling work on site and the person booking any required inspections. Give the coordinator a record of both. A photograph is supporting evidence, not an inspection approval.
Which photographs are useful?
Agree the evidence list with the local professionals. It might include the exposed condition, the specified insulation and underlay, junction details and later finished views. Use the approved design and specification to decide what matters; this is not a technical roofing specification.
Each set needs the job reference, roof area, date, stage and person recording it. Keep a wide view for location and closer views for the detail. Retain original files and the local checker's written note.
Never ask an untrained client to climb up for a better shot. Arrange evidence through the people equipped to work safely on site.
What happens if stripping reveals a problem?
Illustrative example, not one of my jobs: a Manchester homeowner is replacing a pitched roof while their coordinator works from Dublin. The roofer exposes timber that needs assessment before the specified covering can go back.
The local lead makes the area safe and arranges the appropriate assessment. The coordinator logs the finding against the scope, then obtains a written proposal covering the repair, price and programme effect. The authorised client agrees the change before routine additional work proceeds.
The file retains the original condition, the approved repair and the evidence before concealment. That gives the eventual handover something solid to refer to.
How do you avoid holding up the site from Dublin?
Set an evidence-review window and an escalation contact before stripping starts. Let the local lead plan safe temporary protection and weather decisions. A remote admin must not force unsafe work to meet a photo deadline.
Keep separate entries for evidence received, required local checks completed and permission to proceed under the agreed site process. Silence from the office should never be recorded as an inspection pass.
How does this feed the final handover?
Match the completed roof to the current scope and variations. Collect required completion documents, the client's response and any snag owner. Reconcile invoices using the agreed contract terms; do not treat an uploaded photo as automatic payment approval.
Do I need a particular app?
No. A labelled folder and stage register are enough to start. Plan@Job's contractor page describes organising work stages; this guide assumes no country eligibility.
Does coordinating from Dublin settle business permission?
No. Check any Irish immigration permission that applies separately. Irish Immigration Service guidance, checked 22 November 2026. Agree the first hold point before anyone strips the roof.